Trimmer Walk

Project description

The project required the conversion of an underground car park into offices and a communication centre for the relocation of the IT department of Hounslow Police force.

Delivered under a standard JCT Contract, significant logistical issues had to be overcome to deliver the project to meet the client’s very tight deadlines. Timely completion allowed the client to move to the new premises and retain ongoing services provision.

Project details

Client
Lampton 360 / Hounslow Council

Contract period
24 weeks

Contract value
£1.6m

Key facts

  • ✓Large scale air handling, plant and air conditioning installation
  • ✓Control of multiple disciplines and coordination of specialist works to deliver to tight time scales
  • ✓Maintaining police and council working facilities during the construction programme